Weathering the Storm with Quality Liners: Advanced Stormwater Rehabilitation
Tackling severe stormwater infiltration, Clearflo Specialised Services deployed SAERTEX-LINER and Rausch RRcure 100 SE for a critical TAFE Queensland infrastructure upgrade.
A site at TAFE Queensland Eagle Farm Campus saw Clearflo Specialised Services overcome extreme root and concrete infiltration using advanced trenchless technology from SAERTEX multiCom and Rausch Rehab, delivering a long-term structural solution with minimal disruption.
This was one of the first stormwater rehabilitation projects in Queensland to use the SAERTEX-LINER® MULTI Type S+ Standard in combination with the Rausch RRcure 100 SE UV system, technologies available in Australia and New Zealand.
Overcoming Severe Stormwater Infiltration
When Clearflo Specialised Services was awarded the contract to rehabilitate 450m of deteriorated stormwater pipe at TAFE Queensland Eagle Farm Campus in Brisbane, the crew faced some of the worst root and concrete infiltration they had ever encountered.
With support from Pipe Core and access to innovative technology from Rausch Rehab and SAERTEX multiCom, Clearflo Specialised Services delivered a structural renewal solution which the manufacturer said has a technical service life of 100 years, setting a new benchmark for trenchless rehabilitation in complex high-traffic sites.
The site, located in Brisbane’s eastern industrial hub of Eagle Farm, was experiencing major stormwater blockages. More than 90 per cent of the pipe network was obstructed, choked by invasive roots from large Moreton Bay Fig trees along with severe concrete in the lines.
Clearflo Specialised Services Owner John Farrugia said he had never seen such severe infiltration.
“We had over 200m of tree roots to cut before we could even clean the line properly,” he said.
To overcome the challenge, Clearflo Specialised Services engaged TDG Environmental, an experienced specialist in asset investigations, renewals, and maintenance. They conducted high-pressure robotic cutting and ultra-high-pressure water jetting to clear the obstacles. Once the area was cleared, the relining program could begin, carefully staged to maintain access and minimise disruption to operations for TAFE Queensland.
Maintaining Safety And Campus Accessibility
Throughout the project, Clearflo Specialised Services maintained close communication with TAFE Queensland facilities staff, who commended the crew’s professionalism, safety protocols, and ability to keep the site accessible during term time. Temporary fencing was erected around access chambers and pedestrian paths to ensure safety.
Advanced UV-Cured Liner Installation
Over a four-week period, the crew rehabilitated multiple sections of pipe, relining one lane at a time. Conduit lengths ranged from 15-68m, with diameters from DN150-300. The crew also completed multiple junction reinstatements and relined over 100m of DN450 mains using SAERTEX-LINER MULTI Type S+ Standard, a glass-reinforced liner from SAERTEX multiCom, cured using the Rausch RRcure 100 SE UV system.
The liner was chosen for its long technical service life – which SAERTEX has independently tested to 100 years – structural performance, and thin wall thickness, making it an ideal match for confined spaces and approved for use in Queensland.
“SAERTEX multiCom has been great to work with,” Farrugia said. “Their team is upfront about what the product can and can’t do. That transparency helps avoid project risk and builds trust.”
Compact Equipment For Restricted Access
To support the project, Clearflo Specialised Services invested in the Rausch RRcure 100 SE, a self-contained UV curing system available through Pipe Core. Designed for diameters between DN150 and DN1000, it’s well-suited to access-limited sites like schools and carparks.
The Eagle Farm site was experiencing major stormwater blockages.
“The size of the RRcure 100 SE is what appealed to us,” Farrugia said. “It fits into tight spaces. We’ve now completed eight jobs with it, and this TAFE Queensland project was the first time it was used consistently across four weeks.”
To streamline operations, Clearflo Specialised Services custom-built a van with a ramp to house the curing system, enabling quick and safe deployment on site.
Training And Workforce Development
Founded in 2000, Clearflow Specialised Services has grown into a multi-vehicle operation. The crew has continually invested in training and upskilling to ensure operational confidence and system reliability.
“We sent a crew member to Germany for hands-on training with the Rausch Rehab system,” Farrugia said.
This project also supported workforce development, with a Queensland-based crew completing certified theoretical and practical training in SAERTEX-LINER® installation method for both gravity and pressure pipe systems.
“Knowledge is power,” said Farrugia. “The more we understand the system, whether it’s fault finding, terminations, or diagnostics, the less downtime we have and the less frustration for the crew.”
“The ability to access global expertise combined with local support has been a key part of the project’s success. Having that level of support available has been invaluable. The industry is moving forward thanks to this kind of innovation and collaboration.”
Project Benefits
- Long-term durability with an expected technical service life of 100 years
- Trenchless installation with minimal community disruption
- Improved flow capacity of stormwater network
- Fast, efficient, UV-cured liner installation
- Compact equipment easy to use in restricted areas
- Efficient scheduling with reduced site downtime
- Local upskilling and capability development
Delivering Long-Term Stormwater Infrastructure Solutions
Despite the intensive preparation required to clear the stormwater lines, the project was delivered on time and within budget. Most importantly, it future-proofed a critical asset in Brisbane’s stormwater infrastructure, ensuring the site is compliant and ready for redevelopment.
Frequently Asked Questions(FAQ)
1. What is trenchless stormwater rehabilitation?
Trenchless stormwater rehabilitation is a method of repairing or renewing damaged underground drainage pipes without extensive excavation. It uses specialised lining technologies to restore pipeline integrity while minimising surface disruption.
2. What is UV-cured pipe lining?
UV-cured pipe lining is a trenchless rehabilitation technique where a liner is installed inside an existing pipe and cured using ultraviolet light. This creates a structural lining that helps rehabilitate deteriorated pipelines.
3. What are the benefits of using quality liners for stormwater rehabilitation?
Quality liners provide long-term durability, reduce excavation requirements, minimise surface disruption and support efficient pipeline rehabilitation. They are suitable for addressing various underground infrastructure challenges.
4. How long can a structural pipe liner last?
The expected service life depends on the liner system, installation quality and operating conditions. In the Eagle Farm Campus project, the selected SAERTEX-LINER MULTI Type S+ technology offered an expected technical service life of 100 years.
5. Can trenchless technology rehabilitate pipes with severe blockages?
Yes. Trenchless rehabilitation can address severely obstructed pipelines following appropriate preparation. Robotic cutting and high-pressure water jetting can help remove obstructions and prepare pipes for liner installation.